Set and track monthly goals

Goals compare recorded working hours with a monthly target. Set up the resource's baseline, then view progress alongside daily time registration.

Scenario

At Dæmi ehf., a resource works at 80% and has a goal of 75% of working hours after leave. If the monthly line has 160 baseline hours and no leave, working hours become 128 and the goal is 96 hours.

Before you start

Goals are enabled and you have RdN Goals Permission through Settings. The resource uses time registration.

Prepare the calculation

In Time Registration Setup, select a Base Calendar with the correct holidays and Default Work Hours Per Day. The default hours value is 7.35, so check that it suits the company.

Enter projects and tasks for leave and sickness in the non-working task list. Recalculate Leave updates the leave flag on existing non-personal time entries; this is separate from recalculating goal hours.

Walkthrough

  1. Open Time Registration Goals.
  2. Set Default Work (%) to 80 and Default Goal (%) to 75 for the resource. The resource goal card also shows defaults and monthly lines.
  3. Filter the resource number if you do not want to initialize everyone, then choose Initialize Goals.
  4. Choose From Month and To Month. Keep Skip Existing Months enabled to retain existing lines, then confirm.
  5. Inspect the monthly lines. Change work percentage or goal on a line if that month should differ from the defaults.
  6. Open the calendar and compare Registered Hours with Goal (Month) and Goal (To Date).

Result

A goal line exists for each selected month and resource. Registered hours count non-personal work not marked as leave; they are not restricted to approved or chargeable time.

Monthly Goal Totals shows summed hours, resource counts and average percentages. Show Resource Goals opens the underlying lines and Revalidate Goal Hours recalculates them from the calendar and entries. After changing holidays or leave classification, run the recalculation. ValidateGoalMonths revalidates the date on existing monthly lines but does not create missing ones; use Initialize Goals for that.

What can go wrong

If progress is missing, check that a monthly line exists. If figures are wrong, check the base calendar, hours per day, percentages and leave classification. See Goals.